No.347 of 650 · approved, not built MP: Anna Gelderd (Labour) England

South East Cornwall

South East Cornwall has 1.9 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 700 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 40,947 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
1.9 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 700 homes. Approved at least two years ago; waiting on the grid, not on planning.
6 projects · planning database (REPD), July 2026 · how we worked this out
£3.8m
is what the grid gap costs this constituency's 40,947 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 6 waiting projects · years since approval
Station Road, Kelly Bray - Solar Panel 0.2 MW
4.0 YRS
Morrisons Superstore, Plymouth Road - Solar Photovoltaic System 0.4 MW
3.7 YRS
Collon Barton, St Veep - Solar Arrays 0.1 MW
3.7 YRS
Trenake Farm, Pelynt - Solar PV Array 0.2 MW
3.6 YRS
Spinnaker International Spinnaker House, Long Acre - Solar Panels 0.2 MW
2.7 YRS
Connon Bridge - Solar Array 0.9 MW
2.1 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Connon Bridge - Solar ArraySolar Photovoltaics300 homes0.9 MW2024-072.1 yrs
Morrisons Superstore, Plymouth Road - Solar Photovoltaic SystemSolar Photovoltaics100 homes0.4 MW2022-113.7 yrs
Trenake Farm, Pelynt - Solar PV ArraySolar Photovoltaics100 homes0.2 MW2022-123.6 yrs
Station Road, Kelly Bray - Solar PanelSolar Photovoltaics100 homes0.2 MW2022-084.0 yrs
Spinnaker International Spinnaker House, Long Acre - Solar PanelsSolar Photovoltaics100 homes0.2 MW2023-122.7 yrs
Collon Barton, St Veep - Solar ArraysSolar Photovoltaics100 homes0.1 MW2022-113.7 yrs

Plus 1 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
West Kingsmill, Landulph - Battery Storage80 MWapproved, not built 2025could supply ≈280,000 homes
Landulph, Ellbridge Lane - Battery Storage Facility50 MWapproved, not built 2023could supply ≈175,000 homes
Landulph Substation, Ellbridge Lane - Battery Energy Storage50 MWapproved, not built 2023could supply ≈175,000 homes
Trevol Business Park10 MWapproved, not built 2019could supply ≈35,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →