 "pcon24cd": "E14001486",
 "name": "South East Cornwall",
 "nation": "England",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 1.9,
  "stuck_mw_int": 2,
  "stuck_sites": 6,
  "homes_equivalent": 700,
  "homes_vs_seat_households": 0.02,
  "stuck_mw_12m_cut": 2.5,
  "consented_not_built_mw_any_age": 2.5,
  "operational_mw": 118.7,
  "operational_homes_equivalent": 43000,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 1.4,
  "rank": 347,
  "tech_mix": {
   "solar": 1.9
  },
  "tech_summary": "all solar",
  "waiting_vs_running": 0.0,
  "projects": [
   {
    "site_name": "Connon Bridge - Solar Array",
    "repd_ref_id": 10610,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.9,
    "homes_equivalent": 300,
    "consented": "2024-07-09",
    "months_waiting": 24.8,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "China Fleet Country Club - Solar Array",
    "repd_ref_id": 17388,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.6,
    "homes_equivalent": 200,
    "consented": "2024-12-18",
    "months_waiting": 19.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Morrisons Superstore, Plymouth Road - Solar Photovoltaic System",
    "repd_ref_id": 12462,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.4,
    "homes_equivalent": 100,
    "consented": "2022-11-17",
    "months_waiting": 44.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Trenake Farm, Pelynt - Solar PV Array",
    "repd_ref_id": 12566,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2022-12-13",
    "months_waiting": 43.7,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Station Road, Kelly Bray - Solar Panel",
    "repd_ref_id": 11749,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2022-08-15",
    "months_waiting": 47.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Spinnaker International Spinnaker House, Long Acre - Solar Panels",
    "repd_ref_id": 15178,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2023-12-07",
    "months_waiting": 31.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Collon Barton, St Veep - Solar Arrays",
    "repd_ref_id": 12318,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.1,
    "homes_equivalent": 100,
    "consented": "2022-11-24",
    "months_waiting": 44.3,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 40947,
  "seat_total_gbp": 3800000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 0.0,
  "approved_mw": 190.0,
  "approved_24m_mw": 110.0,
  "refused_mw": 0.0,
  "submitted_mw": 0.0,
  "sites": [
   {
    "site_name": "West Kingsmill, Landulph - Battery Storage",
    "capacity_mw": 80.0,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 280000
   },
   {
    "site_name": "Landulph, Ellbridge Lane - Battery Storage Facility",
    "capacity_mw": 49.9,
    "status": "approved",
    "year": 2023,
    "homes_while_discharging": 175000
   },
   {
    "site_name": "Landulph Substation, Ellbridge Lane - Battery Energy Storage",
    "capacity_mw": 49.9,
    "status": "approved",
    "year": 2023,
    "homes_while_discharging": 175000
   },
   {
    "site_name": "Trevol Business Park",
    "capacity_mw": 10.0,
    "status": "approved",
    "year": 2019,
    "homes_while_discharging": 35000
   },
   {
    "site_name": "Battery Box - Birch House - Micro Energy Storage Facility",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 700
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "West Kingsmill, Landulph - Battery Storage",
   "repd_ref_id": 13687,
   "technology": "Battery",
   "capacity_mw": 80.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-07-18",
   "refused": null,
   "planning_authority": "Cornwall",
   "planning_ref": "PA24/09330",
   "operator": "Boultbee Brooks Real Estate Hereford Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-07-18",
     "years_since_consent": 1.0
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Landulph, Ellbridge Lane - Battery Storage Facility",
   "repd_ref_id": 12697,
   "technology": "Battery",
   "capacity_mw": 49.9,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2023-02-06",
   "refused": null,
   "planning_authority": "Cornwall",
   "planning_ref": "PA22/10000",
   "operator": "Pivoted Power Llp",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-02-06",
     "years_since_consent": 3.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Landulph Substation, Ellbridge Lane - Battery Energy Storage",
   "repd_ref_id": 13461,
   "technology": "Battery",
   "capacity_mw": 49.9,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2023-09-05",
   "refused": null,
   "planning_authority": "Cornwall",
   "planning_ref": "PA23/01323",
   "operator": "Conrad Energy",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-09-05",
     "years_since_consent": 2.9
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Trevol Business Park",
   "repd_ref_id": 7404,
   "technology": "Battery",
   "capacity_mw": 10.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2019-09-02",
   "refused": null,
   "planning_authority": "Cornwall",
   "planning_ref": "PA19/03228",
   "operator": "Londonwide Properties",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 7 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2019-09-02",
     "years_since_consent": 6.9
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "E14001508",
  "E14001385",
  "E14001552"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}