No.161 of 650 · approved, not built MP: Dr Caroline Johnson (Conservative) England

Sleaford and North Hykeham

Sleaford and North Hykeham has 44 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 16,000 homes. Britain's grid bottlenecks still add to bills here: about £116 a year per household, £4.8m across the constituency's 41,558 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
44 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 16,000 homes. Approved at least two years ago; waiting on the grid, not on planning. That is 0.7× the renewable capacity actually running here.
12 projects · planning database (REPD), July 2026 · how we worked this out
£4.8m
is what the grid gap costs this constituency's 41,558 households in a year between them — £116 each, about 65 days of one home's electricity.
The £116 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 12 waiting projects · years since approval
Branston Solar Park (extension) 40 MW
8.9 YRS
Barn Farm, Navenby - Solar Panels 0.2 MW
4.5 YRS
Boothby Graffoe - Solar photovoltaics panels 0.2 MW
4.5 YRS
Skinnand Manor Farm, Navenby - Solar panels
4.5 YRS
Cargill & Frontier Agriculture, Camp Road - Solar Panels 0.4 MW
3.6 YRS
Noble Foods, Hives Lane - Solar Panels 0.4 MW
3.3 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Branston Solar Park (extension)Land Between, Mere Road and Sleaford Road, Branston, Lincoln, LincolnshireSolar Photovoltaics15,000 homes40.0 MW2017-128.9 yrs
Swinderby Quarry - Solar PV ArraySwinderby Quarry, Witham St Hughes, LincolnSolar Photovoltaics400 homes1.2 MW2023-113.0 yrs
Pilgrims Pride, Sleaford Road - Solar PanelsPilgrim's UK Ltd Sleaford Road RuskingtonSolar Photovoltaics300 homes0.7 MW2024-082.2 yrs
Beeswax Dyson Farming, Cyclone Way - Solar ArraysBeeswax Dyson Farming Limited, Estates Office, Cyclone Way, Nocton, LincolnSolar Photovoltaics200 homes0.5 MW2024-072.4 yrs
Pilgrims UK, Sleaford Road - Solar CanopyPilgrim's UK Ltd Sleaford Road RuskingtonSolar Photovoltaics200 homes0.5 MW2024-082.2 yrs
Noble Foods, Hives Lane - Solar PanelsNoble Foods Limited, Hives Lane, North ScarleSolar Photovoltaics100 homes0.4 MW2023-073.3 yrs
Cargill & Frontier Agriculture, Camp Road - Solar PanelsCargill Plc And Frontier Agriculture Camp Road Witham St HughsSolar Photovoltaics100 homes0.4 MW2023-033.6 yrs
Barn Farm, Navenby - Solar PanelsBarn Farm Lowfields NavenbySolar Photovoltaics100 homes0.2 MW2022-054.5 yrs
Boothby Graffoe - Solar photovoltaics panelsLowfields Farm Castle Lane Boothby Graffoe LincolnSolar Photovoltaics100 homes0.2 MW2022-054.5 yrs
North Kesteven Sports Centre, Moor Lane - Solar PV PanelsNorth Kesteven Sports Centre, Moor Lane, North Hykeham, LincolnSolar Photovoltaics100 homes0.2 MW2024-072.3 yrs
Skinnand Manor Farm, Navenby - Solar panelsSkinnand Manor Farm Parsons Lane Navenby LincolnSolar Photovoltaics—— MW2022-054.5 yrs
The Feed Mill, Lowfields - Solar PanelsThe Feed Mill, Lowfields, Navenby, LincolnSolar Photovoltaics—— MW2024-032.6 yrs

Plus 3 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Hill Rise, Coleby - Battery Energy Storage1,000 MWcould supply ≈3,504,000 homes
Beacon Fen Energy Park600 MWapproved, not built 2026could supply ≈2,102,000 homes
Green Man Road, Navenby - Battery Storage400 MWcould supply ≈1,402,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Dr Caroline Johnson said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)