North East Hertfordshire has 75 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 27,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.0m across the constituency's 43,215 homes. A 50 MW battery was refused planning here in 2025; while discharging it could have supplied about 175,000 homes.

Ranks 91 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Ginns Road, Stocking Pelham - Battery Energy StorageFRV TH Powertek Limited Battery
400 MW
Cannot connect to the grid until 2034, 9 years after it was approvedWho can move it: the grid operator (NESO) and National Grid
Beane Solar Farm - Solar PanelsRenewable Energy Systems RES ltd (Beaufort) Battery
354 MW
Waiting 1.6 years for a planning decisionWho can move it: East Hertfordshire Council
Westfield Conservation Park - Battery Energy StorageLightrock Power Limited Battery
99 MW
Applied in 2025, still waiting for a decisionWho can move it: North Hertfordshire Council