CONSTITUENCY BRIEFING · ENERGYMAP.APP

North East Fife

MP: Wendy Chamberlain (Liberal Democrat) Scotland Data to July 2026

North East Fife has 21 MW of clean power (mostly onshore wind) approved and still not built: enough to supply a year's electricity to 14,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.8m across the constituency's 40,975 homes.

Ranks 196 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
FerrymuirGore Street Energy Storage Fund Battery
50 MW
Cannot connect to the grid until 2022, 2 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission
Duniface Gas Peaking Plant - Battery Energy Storage Forsa Energy Gas Holdings Limited Battery
50 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
West Springfield Solar Farm - Solar Panels & BESSBLC Energy Solar 18,000 homes
50 MW
Waiting 1.3 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects)

What else is in the briefing