CONSTITUENCY BRIEFING · ENERGYMAP.APP

Ely and East Cambridgeshire

MP: Charlotte Cane (Liberal Democrat) England Data to July 2026

Ely and East Cambridgeshire has 145 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 53,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.1m across the constituency's 44,828 homes. A 90 MW battery was refused planning here in 2026; while discharging it could have supplied about 315,000 homes.

Ranks 36 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Wicken Bridleway, Church Road - Battery Energy StoraGreen Switch Capital Limited Battery
400 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Land Southwest of Hightown Drove, Burwell - Battery Grenergy Renewables UK Limited Battery
90 MW
Refused by East Cambridgeshire Council in 2026Who can move it: East Cambridgeshire Council
Newmarket Road, Bottisham - Battery Energy StorageRidge Clean Energy Limited Battery
50 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.