No.191 of 650 · approved, not built MP: Jim Allister (Traditional Unionist Voice) Northern Ireland

North Antrim

North Antrim has 22 MW of clean power (all onshore wind) approved and still not built: enough to supply a year's electricity to 19,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. Northern Ireland is on the all-Ireland grid, so Britain's grid bottlenecks do not reach bills here in the same way. There is also 119 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Not visible
here
119 MW of wind is running in this constituency, but it sits on the local network rather than the national grid — so if it is paid to switch off, no national record shows it. That is why this seat has no figure here: not because nothing happens, but because nobody publishes it. The £ figure for this seat is a floor, not a zero.
22 MW
of clean power — all onshore wind — approved and still not built, enough to supply a year's electricity to 19,000 homes. Approved at least two years ago; waiting on the grid, not on planning. That is 0.1× the renewable capacity actually running here.
8 projects · planning database (REPD), July 2026 · how we worked this out
Different
grid
Northern Ireland is part of the all-Ireland Single Electricity Market, not the GB grid, so the GB grid-gap bill does not apply here.

The waiting list

6 of 8 waiting projects · years since approval
Islandranny Road 0.3 MW
7.1 YRS
Carmagrim Road 0.2 MW
5.3 YRS
Replacement Wind Turbine 0.1 MW
5.0 YRS
Drumack Lane Replacement Turbine
4.4 YRS
Corkey Windfarm (repowering) 20 MW
4.4 YRS
Moyarget Road 0.3 MW
4.3 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Corkey Windfarm (repowering)Wind Onshore17,000 homes20.0 MW2022-034.4 yrs
93 Caddy Road - Wind TurbineWind Onshore700 homes0.8 MW2023-122.7 yrs
Islandranny RoadWind Onshore300 homes0.3 MW2019-067.1 yrs
Stroan RoadWind Onshore300 homes0.3 MW2022-064.1 yrs
Moyarget RoadWind Onshore300 homes0.3 MW2022-044.3 yrs
Carmagrim RoadWind Onshore200 homes0.2 MW2021-045.3 yrs
Replacement Wind TurbineWind Onshore100 homes0.1 MW2021-075.0 yrs
Drumack Lane Replacement TurbineWind Onshore— MW2022-024.4 yrs

Plus 3 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Energy Storage System Installation in Rasharkin100 MWcould supply ≈350,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →