Morecambe and Lunesdale
Morecambe and Lunesdale has 3.5 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,300 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,896 homes. There is also 25 MW of wind running here on the local network. If that gets switched off, no national record shows it.
Ranks 287 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Fanny House Farm, Bay Gateway - Battery StorageInnova Renewables | Battery | 940 MW |
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company |
| Heysham Energy Storage ProjectKona Energy Limited | Battery | 200 MW |
Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company |
| Bay Gateway - Battery Storage FacilityEnergi Generation | Battery | 200 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
What else is in the briefing
- All 9 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How Morecambe and Lunesdale compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call