CONSTITUENCY BRIEFING · ENERGYMAP.APP

Midlothian

MP: Kirsty McNeill (Labour (Co-op)) Scotland Data to July 2026

Midlothian has 4.2 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,500 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,009 homes.

Ranks 275 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Salters Battery Energy Storage SystemBuccleuch Group Battery
200 MW
Cannot connect to the grid until 2031, 6 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission
Penicuik, Moorfoot Hills - Torfichen Wind FarmRES Limited Onshore wind 94,000 homes
108 MW
Waiting 2.7 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects)
Penicuik, Moorfoot Hills - Torfichen Wind FarmRES Limited Battery
50 MW
Waiting 2.7 years for a planning decisionWho can move it: the Scottish Government (it decides big energy projects)

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.