CONSTITUENCY BRIEFING · ENERGYMAP.APP

Mid Bedfordshire

MP: Blake Stephenson (Conservative) England Data to July 2026

Mid Bedfordshire has 43 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 16,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.7m across the constituency's 40,057 homes.

Ranks 155 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Sundon, Chalton - Battery Energy Storage SystemStatera Energy Battery
500 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Toddington Services, Hipsey Spinney - Battery StoragKona Energy Limited Battery
250 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Sundon Sub Station Battery Storage FacilityClearstone Energy Limited Battery
50 MW
Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing