Mid and South Pembrokeshire
Mid and South Pembrokeshire has 9.5 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 3,400 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 45,486 homes.
Ranks 231 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Pembroke Power Station, Pwllcrochan - Battery StoragRWE Generation UK Plc | Battery | 350 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
| Goldborough Road, Hundleton - Battery Energy StoragePembroke Green Limited (Enso Energy and Cero G | Battery | 350 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
| Pembroke Power Station, Pwllcrochan - Hydrogen ProduRWE Generation UK Plc | Hydrogen | 110 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
What else is in the briefing
- All 15 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How Mid and South Pembrokeshire compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 2 story angles for local reporting