No.51 of 650 · approved, not built MP: Gregor Poynton (Labour) Scotland

Livingston

Livingston has 118 MW of clean power (mostly onshore wind) approved and still not built: enough to supply a year's electricity to 91,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,193 homes. There is also 64 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Not visible
here
64 MW of wind is running in this constituency, but it sits on the local network rather than the national grid — so if it is paid to switch off, no national record shows it. That is why this seat has no figure here: not because nothing happens, but because nobody publishes it. The £ figure for this seat is a floor, not a zero.
118 MW
of clean power — mostly onshore wind — approved and still not built, enough to supply a year's electricity to 91,000 homes — 2 times every household in this constituency. Approved at least two years ago; waiting on the grid, not on planning. That is 1.0× the renewable capacity actually running here.
10 projects · 95 MW onshore wind, 23 MW solar · planning database (REPD), July 2026 · how we worked this out
£4.1m
is what the grid gap costs this constituency's 44,193 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

4 of 10 waiting projects · years since approval
Longhill Burn Wind Farm 46 MW
6.3 YRS
Camilty Plantation - Wind Farm 26 MW
4.8 YRS
Pearie Law 2 - Wind turbines 14 MW
4.6 YRS
Selms Muir - Solar Farm 18 MW
3.9 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Longhill Burn Wind FarmWind Onshore40,000 homes45.6 MW2020-046.3 yrs
Camilty Plantation - Wind FarmWind Onshore23,000 homes25.8 MW2021-104.8 yrs
Selms Muir - Solar FarmSolar Photovoltaics6,500 homes18.0 MW2022-093.9 yrs
Pearie Law 2 - Wind turbinesWind Onshore13,000 homes14.4 MW2021-124.6 yrs
Tormywheel Wind Farm ExtensionWind Onshore4,400 homes5.0 MW2020-036.4 yrs
Harburnhead Windfarm - Wind TurbineWind Onshore3,500 homes4.0 MW2023-013.5 yrs
Nettlehill Road - Solar PanelsSolar Photovoltaics1,000 homes2.8 MW2024-022.4 yrs
The Wyman Gordon Facility, Nettlehill Road- Solar FarmSolar Photovoltaics700 homes2.0 MW2023-013.6 yrs
Uphall Business Park, Uphall - Solar PV PanelsSolar Photovoltaics100 homes0.3 MW2022-034.4 yrs
Maxwell Square, Brucefield - Solar PanelsSolar Photovoltaics100 homes0.2 MW2023-073.0 yrs

Plus 3 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Learielaw Farm, Learielaw - Battery Energy Storage100 MWapproved, not built 2025could supply ≈350,000 homes
Drumshoreland Road Battery Storage Facility50 MWapproved, not built 2022could supply ≈175,000 homes
Drumcross Battery Storage30 MWapproved, not built 2018could supply ≈105,000 homes
Broxburn20 MWoperating 2017could supply ≈70,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →