Cardiff South and Penarth

MP: Stephen Doughty (Labour (Co-op)) Wales Data to July 2026

Cardiff South and Penarth has 25 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 9,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,951 homes. A 50 MW battery was refused planning here in 2025; while discharging it could have supplied about 175,000 homes.

Ranks 183 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Rover Way, Splott - Energy Park & Data CentreLatos Cardiff Limited Battery
1,000 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Pen Y Maes, Ashby Road - Battery Energy StorageRoot Power South Limited Battery
50 MW
Refused by Vale of Glamorgan Council in 2025Who can move it: Vale of Glamorgan Council
Sully Moors Road - Battery Energy Storage FacilityCentrica Plc Head Office Battery
50 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.