CONSTITUENCY BRIEFING · ENERGYMAP.APP

Calder Valley

MP: Josh Fenton-Glynn (Labour) England Data to July 2026

Calder Valley has 1.4 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 500 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,850 homes.

Ranks 380 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Ashday Hall Farm, Ashday Lane - Battery Energy StoraSandbrook Capital Bes Limited Battery
65 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Lowfields Energy Storage ProjectUK Battery Storage Battery
50 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.