Caerphilly
Caerphilly has 112 MW of clean power (mostly onshore wind) approved and still not built: enough to supply a year's electricity to 88,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £116 a year per household, £4.8m across the constituency's 41,345 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Twyn Hywel Wind FarmEglwysilan Common, N/O Senghenydd, Caerphilly | Wind Onshore | 81,000 homes | 92.4 MW | 2024-11 | 2.0 yrs |
| Cwm Ivor Penyrheol Solar FarmCwm Ivor Penyrheol Caerphilly | Solar Photovoltaics | 7,300 homes | 20.0 MW | 2024-05 | 2.5 yrs |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →