CONSTITUENCY BRIEFING · ENERGYMAP.APP

Brigg and Immingham

MP: Martin Vickers (Conservative) England Data to July 2026

Brigg and Immingham has 46 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 17,000 homes. Britain's grid bottlenecks still add to bills here: about £116 a year per household, £4.6m across the constituency's 39,883 homes. A 30 MW battery was refused planning here in 2026; while discharging it could have supplied about 105,000 homes.

Ranks 157 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Sweetbriar Farm - Battery Energy Storage SystemLightrock Power Limited Battery 800 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA/2025/794
Stallingboroughe, Stallingborough Road - BESSIsland Green Power Battery 375 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DM/0455/25/FUL
Stallingborough Road - Battery StorageIsland Green Power Battery 125 MW Waiting 13 months for a planning decisionWho can move it: West Lindsey Council · planning ref WL/2025/00667
Killingholme Power Station, Chase Hill Road - Hydrogen Production FacilityUniper UK Limited Hydrogen 120 MW Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA/2025/1146
South Humber Bank Power StationEggborough Power (EP SHB) EfW Incineration 95 MW Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref EN010107
Trondheim Way Battery energy storageVox Burns Limited Battery 80 MW Under constructionWho can move it: the developer · earliest connection 2027 (in construction) · planning ref DM/0120/21/FUL
Netherlands Way - Battery Energy FacilityVolta Energy Group Battery 80 MW Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DM/0762/21/FUL
Europa Way - Battery Storage FacilityNewton Energi Limited Battery 80 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DM/0484/24/FUL
Winterton Road, Roxby - Solar FarmSolar 2 Limited Solar 50 MW18,000 homes Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref PA/2024/129
Hewitts Avenue, New Waltham - Battery StorageHarmony HS (JB) Limited Battery 50 MW Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DM/0158/24/FUL
Scawby Road - Solar ArrayBrockwell Storage & Solar Limited Solar 50 MW18,000 homes Refused by North Lincolnshire Council in 2026Who can move it: North Lincolnshire Council · planning ref PA/2025/292
Immingham Solar Farm - Solar FarmOne Planet Developments Limited Solar 50 MW18,000 homes Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company · planning ref DM/0108/24/FUL

Plus 15 smaller projects — see the full seat page.

Compared with its neighbours

ConstituencyApproved, not builtRunningPaid to switch off
Brigg and Immingham 46 MW142 MWnot visible
Gainsborough 1,184 MW48 MWnot visible
Scunthorpe 219 MW71 MWnot visible
Louth and Horncastle 15 MW96 MWnot visible
Great Grimsby and Cleethorpes 45 MW2.2 MWnot visible

Gainsborough next door has 1,184 MW waiting, more than Brigg and Immingham's 46 MW.

The rest of the briefing

  • Every approval each project still needs, and which of them the public can see
  • What building them would mean here — community payments, business rates and construction work
  • Drafted parliamentary questions and letters, filled in with this seat's figures
  • 3 story angles for local reporting
  • A two-page PDF, and a newsroom edition with the references and who to call
FREE ACCOUNT · NO PASSWORD

Sets which edition you land on. We do not check it, and you can switch on any page.

Everything above needs no account, and neither does the full seat page, the method or this constituency's raw data. The account covers the packaged briefing and its PDF, and nothing else.