Bradford West has 2.3 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 800 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.6m across the constituency's 39,290 homes.

Ranks 328 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Bradford West, Harrop Lane, Wilsden - Battery Storag24 Power Limited Battery
100 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company
Peat Dykes Farm, Harrop Lane - Battery Energy StoragBrockwell Storage & Solar Limited Battery
100 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Old Allen Road, Wilsden - Battery Energy Storage SysRenewable Connections Developments Limited Battery
100 MW
Applied in 2025, still waiting for a decisionWho can move it: Bradford Council