CONSTITUENCY BRIEFING · ENERGYMAP.APP

Bicester and Woodstock

MP: Calum Miller (Liberal Democrat) England Data to July 2026

Bicester and Woodstock has 112 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 41,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,359 homes.

Ranks 55 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Botley West, Botley - Botley West Solar ProjectPhotovolt Development Partners / SolarFive Solar 305,000 homes
840 MW
Waiting 1.7 years for a planning decisionWho can move it: the Planning Inspectorate (it decides nationally significant projects)
Woodstock Road, Yarnton - Battery Energy Storage SysRenewable Connections Developments Limited Battery
52 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Tar Solar FarmBluefield Renewable Developments Limited Solar 18,000 homes
50 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.