No.10 OF 650 · APPROVED, NOT BUILT MP: Brendan O'Hara (Scottish National Party) Scotland

Argyll, Bute and South Lochaber

Argyll, Bute and South Lochaber was paid £1.7m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 21 days. A further 384 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 338,000 homes. A 56 MW battery approved at High Constellation Wind Farm in 2020 would store power that is currently wasted; it has not been built. A 50 MW battery was refused planning here in 2024; while discharging it could have supplied about 175,000 homes.

£1.7m
paid to wind farms here not to generate in the last year — enough to pay for every household here's electricity for 21 days.
Elexon balancing data, 12 months to 31 Jul 2026 · No.15 of 19 seats with visible switch-offs · how we worked this out
384 MW
of clean power — almost all onshore wind — approved and still not built, enough to supply a year's electricity to 338,000 homes — 8 times every household in this constituency. Approved at least two years ago; waiting on the grid, not on planning. That is 0.8× the renewable capacity actually running here.
17 projects · 374 MW onshore wind, 9.9 MW hydro, 0.2 MW solar · planning database (REPD), July 2026 · how we worked this out
£4.1m
is what the grid gap costs this constituency's 44,349 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 17 waiting projects · years since approval
Beinn an Tuirc Windfarm Phase 3 50 MW
9.4 YRS
Eascairt Wind Farm 26 MW
7.9 YRS
Tangy 4 Wind Farm 80 MW
6.6 YRS
High Constellation Wind Farm 48 MW
6.1 YRS
Blarghour Wind Farm 84 MW
4.8 YRS
Rowan Wind Farm 86 MW
2.3 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Rowan Wind FarmWind Onshore75,000 homes85.8 MW2024-042.3 yrs
Blarghour Wind FarmWind Onshore73,000 homes84.0 MW2021-104.8 yrs
Tangy 4 Wind FarmWind Onshore70,000 homes80.0 MW2019-126.6 yrs
Beinn an Tuirc Windfarm Phase 3Wind Onshore44,000 homes49.9 MW2017-029.4 yrs
High Constellation Wind FarmWind Onshore42,000 homes48.0 MW2020-066.1 yrs
Eascairt Wind FarmWind Onshore23,000 homes26.0 MW2018-097.9 yrs
Glen Noe RiverSmall Hydro2,300 homes2.0 MW2016-099.9 yrs
Allt Easach HydroSmall Hydro2,300 homes2.0 MW2019-037.4 yrs
Glen Etive Estate Phase I (Allt na Chaorainn)Small Hydro1,600 homes1.4 MW2018-087.9 yrs
Allt CharnanSmall Hydro1,100 homes1.0 MW2019-037.4 yrs
Glen Etive Estate Phase II (Allt Mheuran)Small Hydro1,000 homes0.9 MW2019-037.4 yrs
Blackwater DamSmall Hydro900 homes0.8 MW2019-037.4 yrs
Allt EilidhSmall Hydro700 homes0.6 MW2019-087.0 yrs
Craig FarmSmall Hydro500 homes0.4 MW2019-047.3 yrs
Garvie BurnSmall Hydro500 homes0.4 MW2019-037.4 yrs
Duror 2 Hydro SchemeSmall Hydro500 homes0.4 MW2019-037.4 yrs
Glenegedale Lotts, Turbine Lotts - Solar Pv ArraySolar Photovoltaics100 homes0.2 MW2024-062.1 yrs

Plus 9 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Cnoc Buidhe Windfarm109 MWcould supply ≈381,000 homes
High Constellation Wind Farm56 MWapproved, not built 2020could supply ≈194,000 homes
Ardencaple Farm - Battery Storage50 MWrefused 2024could supply ≈175,000 homes
SSE Taynuilt Substation - Battery Energy Storage50 MWapproved, not built 2025could supply ≈175,000 homes
Ladyfield Renewable Energy Park41 MWapproved, not built 2025could supply ≈145,000 homes
Sheirdrim Renewable Energy Development - Battery38 MWrefused 2023could supply ≈133,000 homes
Clachaig Glen30 MWapproved, not built 2024could supply ≈105,000 homes
Earraghail Renewable Energy Development25 MWrefused 2025could supply ≈88,000 homes
Corr Chnoc Wind Farm25 MWcould supply ≈88,000 homes
Giants Burn Wind Farm -Batter Energy Storage23 MWcould supply ≈81,000 homes
West Torrisdale Wind Farm20 MWcould supply ≈70,000 homes
Cruach Clenamacrie Wind Farm20 MWcould supply ≈70,000 homes

Wind farms paid to switch off

12 months to 31 Jul 2026 · mapping confidence shown · mapping file
SitePaid, 12 monthsEnergy lostConfidence
Carraig Gheal£1.7ma year of 8,600 homes' electricityhigh
Cour Wind Farm£4ka year of 0 homes' electricityhigh

What this page does not show

The switch-off figure covers the big wind farms on the national grid only; smaller farms on the local grid are switched off invisibly, so it is a floor. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Brendan O'Hara said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)