CONSTITUENCY BRIEFING · ENERGYMAP.APP

Aberafan Maesteg

MP: Stephen Kinnock (Labour) Wales Data to July 2026

Aberafan Maesteg was paid £470k last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 6.4 days. A further 37 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 32,000 homes. A 100 MW battery approved at Rhydypandy Road, Morriston in 2025 would store power that is currently wasted; it has not been built.

Ranks 162 of 650 for clean power approved and not built; 17 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Y Bryn Wind FarmESB / Coriolis Energy Onshore wind 114,000 homes
130 MW
Refused by Welsh Government (NSIP) Council in 2025Who can move it: Welsh Government (NSIP) Council
Rhydypandy Road, Morriston - Battery Energy Storage Statkraft UK Battery
100 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Foel TrawsnantPennant Walters Ltd Onshore wind 31,000 homes
35 MW
Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.