 "pcon24cd": "W07000081",
 "name": "Aberafan Maesteg",
 "nation": "Wales",
 "number1": {
  "visible": true,
  "cost_gbp_12m": 470000,
  "cost_gbp_12m_exact": 466378,
  "curtailed_mwh_12m": 4858,
  "rank_of_visible": 17,
  "visible_seats": 19,
  "framings": {
   "hours_of_seat_homes_electricity": 153.4,
   "homes_for_a_year_energy_lost": 1900
  },
  "sites": [
   {
    "site_name": "Pen Y Cymoedd",
    "repd_ref_id": 4595,
    "cost_gbp_12m": 470000,
    "curtailed_mwh_12m": 4858,
    "homes_for_a_year": 1900,
    "mapping_confidence": "high"
   }
  ],
  "invisible_wind": {
   "mw": 71.5,
   "sites": 5
  }
 },
 "number2": {
  "stuck_mw": 37.2,
  "stuck_mw_int": 37,
  "stuck_sites": 4,
  "homes_equivalent": 32000,
  "homes_vs_seat_households": 0.79,
  "stuck_mw_12m_cut": 72.2,
  "consented_not_built_mw_any_age": 72.2,
  "operational_mw": 313.3,
  "operational_homes_equivalent": 267000,
  "refused_5y_mw": 130.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 13.7,
  "rank": 162,
  "tech_mix": {
   "onshore wind": 36.5,
   "solar": 0.7
  },
  "tech_summary": "almost all onshore wind",
  "waiting_vs_running": 0.1,
  "projects": [
   {
    "site_name": "Foel Trawsnant",
    "repd_ref_id": 4764,
    "technology": "Wind Onshore",
    "capacity_mw": 35.0,
    "homes_equivalent": 31000,
    "consented": "2021-11-25",
    "months_waiting": 56.2,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Tonmawr - Mynydd Fforch Dwm Wind Farm",
    "repd_ref_id": 11298,
    "technology": "Wind Onshore",
    "capacity_mw": 35.0,
    "homes_equivalent": 31000,
    "consented": "2024-12-23",
    "months_waiting": 19.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Kenfig Industrial Estate, Margam - Wind turbine",
    "repd_ref_id": 11427,
    "technology": "Wind Onshore",
    "capacity_mw": 1.5,
    "homes_equivalent": 1300,
    "consented": "2022-09-29",
    "months_waiting": 46.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Margam - Solar panels",
    "repd_ref_id": 11552,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.4,
    "homes_equivalent": 100,
    "consented": "2022-07-21",
    "months_waiting": 48.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Dyfed Reinforcements, Riverside Road - Solar Panels",
    "repd_ref_id": 11984,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.4,
    "homes_equivalent": 100,
    "consented": "2022-09-29",
    "months_waiting": 46.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Tonmawr - Mynydd Fforch Dwm Wind Farm",
    "repd_ref_id": 11299,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2024-12-23",
    "months_waiting": 19.3,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 40812,
  "seat_total_gbp": 3800000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 22.0,
  "building_mw": 0.0,
  "approved_mw": 130.0,
  "approved_24m_mw": 0.0,
  "refused_mw": 0.0,
  "submitted_mw": 0.0,
  "sites": [
   {
    "site_name": "Rhydypandy Road, Morriston - Battery Energy Storage System",
    "capacity_mw": 100.0,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 350000
   },
   {
    "site_name": "Chosen Park, Baglan Energy Park - Unit 3 - Battery Storage System",
    "capacity_mw": 30.0,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 105000
   },
   {
    "site_name": "Pen y Cymoedd Energy Storage",
    "capacity_mw": 22.0,
    "status": "operating",
    "year": null,
    "homes_while_discharging": 77000
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Y Bryn Wind Farm",
   "repd_ref_id": 10036,
   "technology": "Wind Onshore",
   "capacity_mw": 130.0,
   "homes_equivalent": 114000,
   "status": "Application Refused",
   "consented": null,
   "refused": "2025-11-21",
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "DNS/3264571",
   "operator": "ESB / Coriolis Energy",
   "reason": {
    "reason": "refused",
    "label": "Refused by the Welsh Government (it decides big energy projects) in 2025",
    "who": "the Welsh Government (it decides big energy projects)",
    "evidence": {
     "refusal_date": "2025-11-21"
    },
    "all_matches": [
     "refused"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Rhydypandy Road, Morriston - Battery Energy Storage System",
   "repd_ref_id": 18120,
   "technology": "Battery",
   "capacity_mw": 100.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-12-18",
   "refused": null,
   "planning_authority": "Swansea",
   "planning_ref": "2025/0855/FUL",
   "operator": "Statkraft UK",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-12-18",
     "years_since_consent": 0.6
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Foel Trawsnant",
   "repd_ref_id": 4764,
   "technology": "Wind Onshore",
   "capacity_mw": 35.0,
   "homes_equivalent": 31000,
   "status": "Awaiting Construction",
   "consented": "2021-11-25",
   "refused": null,
   "planning_authority": "Neath Port Talbot",
   "planning_ref": "P2014/0825",
   "operator": "Pennant Walters Ltd",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 5 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2021-11-25",
     "years_since_consent": 4.7
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Tonmawr - Mynydd Fforch Dwm Wind Farm",
   "repd_ref_id": 11298,
   "technology": "Wind Onshore",
   "capacity_mw": 35.0,
   "homes_equivalent": 31000,
   "status": "Awaiting Construction",
   "consented": "2024-12-23",
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "DNS/3255801",
   "operator": "Naturalis Energy Developments Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-12-23",
     "years_since_consent": 1.6
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Chosen Park, Baglan Energy Park - Unit 3 - Battery Storage System",
   "repd_ref_id": 18342,
   "technology": "Battery",
   "capacity_mw": 30.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-06-19",
   "refused": null,
   "planning_authority": "Neath Port Talbot",
   "planning_ref": "P2025/0064",
   "operator": "Aldustria Energy Storage",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-06-19",
     "years_since_consent": 1.1
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Pioneer 2 - Hydrogen Production Facility",
   "repd_ref_id": 18704,
   "technology": "Hydrogen",
   "capacity_mw": 2.5,
   "homes_equivalent": null,
   "status": "Under Construction",
   "consented": "2025-06-23",
   "refused": null,
   "planning_authority": "Neath Port Talbot",
   "planning_ref": "P2025/0222",
   "operator": "Protium Green Hydrogen Supply Limited",
   "reason": {
    "reason": "building",
    "label": "Under construction",
    "who": "the developer",
    "evidence": {},
    "all_matches": [
     "building"
    ]
   },
   "earliest": "2027 (in construction)",
   "tec": null
  },
  {
   "site_name": "Kenfig Industrial Estate, Margam - Wind turbine",
   "repd_ref_id": 11427,
   "technology": "Wind Onshore",
   "capacity_mw": 1.5,
   "homes_equivalent": 1300,
   "status": "Awaiting Construction",
   "consented": "2022-09-29",
   "refused": null,
   "planning_authority": "Neath Port Talbot",
   "planning_ref": "P2022/0372",
   "operator": "Infinite Renewables Group Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 4 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2022-09-29",
     "years_since_consent": 3.8
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "W07000103",
  "W07000086",
  "W07000107",
  "W07000099"
 ],
 "flags": [],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}