Witham
Witham has 24 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 8,600 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,668 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Park Road - Solar Farm | Solar Photovoltaics | 8,200 homes | 22.5 MW | 2023-12 | 2.6 yrs |
| Motus Trucks and Vans, Griggs Way - Solar PV Panels | Solar Photovoltaics | 100 homes | 0.3 MW | 2023-02 | 3.5 yrs |
| The Essex Golf/Leisure Club, The Airfield Earls - Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2023-10 | 2.8 yrs |
| Church Road Tesco | Solar Photovoltaics | 100 homes | 0.2 MW | 2019-11 | 6.7 yrs |
| Cego Limited, Crittall Road - Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2024-04 | 2.3 yrs |
| Howbridge Junior School, Dengie Close - Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2023-08 | 3.0 yrs |
Plus 3 more approved within the last two years.
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| Kentish Farm 2 - Battery Energy Storage | 22 MW | in planning | could supply ≈79,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →