No.193 of 650 · approved, not built MP: Dan Aldridge (Labour) England

Weston-super-Mare

Weston-super-Mare has 25 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 9,000 homes. Britain's grid bottlenecks still add to bills here: about £116 a year per household, £5.0m across the constituency's 43,124 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
25 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 9,000 homes. Approved at least two years ago; waiting on the grid, not on planning.
3 projects · planning database (REPD), July 2026 · how we worked this out
£5.0m
is what the grid gap costs this constituency's 43,124 households in a year between them — £116 each, about 65 days of one home's electricity.
The £116 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

3 of 3 waiting projects · years since approval
Sewage Treatment Works, Warth Lane - Solar Photovoltaic Panels
3.0 YRS
Morrisons, Worle Moor Gate - Solar Photovoltaic Panels 0.3 MW
2.6 YRS
Sandbay, Elmsley Lane, Kewstoke - Solar Farm 24 MW
2.1 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Sandbay, Elmsley Lane, Kewstoke - Solar FarmElmsley Lane KewstokeSolar Photovoltaics8,900 homes24.5 MW2024-102.1 yrs
Morrisons, Worle Moor Gate - Solar Photovoltaic PanelsMorrisons, Worle Moor Gate, Weston Super MareSolar Photovoltaics100 homes0.3 MW2024-032.6 yrs
Sewage Treatment Works, Warth Lane - Solar Photovoltaic PanelsSewage Treatment Works, Warth Lane, Wick St Lawrence, Weston Super MareSolar Photovoltaics—— MW2023-113.0 yrs

Plus 2 more approved within the last two years.

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →