CONSTITUENCY BRIEFING · ENERGYMAP.APP

West Dorset

MP: Edward Morello (Liberal Democrat) England Data to July 2026

West Dorset has 37 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 13,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.0m across the constituency's 43,222 homes.

Ranks 163 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Caswell Farm, Common Lane - Solar FarmGridSource Limited Solar 15,000 homes
40 MW
Applied in 2025, still waiting for a decisionWho can move it: Dorset Council
Higher Stockbridge FarmVoltalia UK Solar 13,000 homes
35 MW
Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company
Caswell Farm, Common Lane - Battery Energy StorageGridSource Limited Battery
20 MW
Applied in 2025, still waiting for a decisionWho can move it: Dorset Council

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.