Weald of Kent has 51 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 18,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.5m across the constituency's 38,312 homes.

Ranks 131 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Stonestreet Green - Solar Farm & Battery StorageEvolution Power Solar 36,000 homes
100 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Sellindge Substation, Church Lane - Battery StoragePivoted Power Llp Battery
57 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company
Glassenbury - Battery Storage SystemGresham House Battery
50 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company