No.181 of 650 · approved, not built MP: Mrs Sharon Hodgson (Labour) England

Washington and Gateshead South

Washington and Gateshead South has 26 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 9,300 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.9m across the constituency's 41,894 homes. A 71 MW battery was refused planning here in 2026; while discharging it could have supplied about 249,000 homes.

Not visible
here
6 MW of wind is running in this constituency, but it sits on the local network rather than the national grid — so if it is paid to switch off, no national record shows it. That is why this seat has no figure here: not because nothing happens, but because nobody publishes it. The £ figure for this seat is a floor, not a zero.
26 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 9,300 homes. Approved at least two years ago; waiting on the grid, not on planning. That is 1.6× the renewable capacity actually running here.
12 projects · planning database (REPD), July 2026 · how we worked this out
£3.9m
is what the grid gap costs this constituency's 41,894 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 12 waiting projects · years since approval
Washington Road - Solar Farm 20 MW
4.7 YRS
Team Valley Trading Estate - Solar Photovoltaic Equipment 0.2 MW
4.4 YRS
Spire Road - Solar Array 0.2 MW
4.3 YRS
Sedling Road - Solar Panels 0.4 MW
4.3 YRS
Griffiths Textiles Machines, Alston Road - Solar Panels 0.7 MW
3.9 YRS
Dacon Fabrications Limited, Dukesway - Solar PV Panels 0.2 MW
3.7 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Washington Road - Solar FarmSolar Photovoltaics7,300 homes20.0 MW2021-124.7 yrs
Snop, Rainhill Road - Solar PanelsSolar Photovoltaics500 homes1.2 MW2023-013.6 yrs
Parker Hannifin Manufacturing - Solar PanelsSolar Photovoltaics400 homes1.1 MW2023-083.0 yrs
Griffiths Textiles Machines, Alston Road - Solar PanelsSolar Photovoltaics300 homes0.7 MW2022-093.9 yrs
Encore Envelopes Limited, Industrial Road - Solar PanelsSolar Photovoltaics200 homes0.5 MW2023-122.7 yrs
Rocket Medical, Sedling Road - Solar PV SystemSolar Photovoltaics200 homes0.4 MW2023-023.5 yrs
Sedling Road - Solar PanelsSolar Photovoltaics100 homes0.4 MW2022-044.3 yrs
Vantec, Turbine Way - Solar PanelsSolar Photovoltaics100 homes0.3 MW2023-063.1 yrs
Vantec, Infiniti Drive - Solar PanelsSolar Photovoltaics100 homes0.3 MW2023-063.1 yrs
Team Valley Trading Estate - Solar Photovoltaic EquipmentSolar Photovoltaics100 homes0.2 MW2022-034.4 yrs
Spire Road - Solar ArraySolar Photovoltaics100 homes0.2 MW2022-034.3 yrs
Dacon Fabrications Limited, Dukesway - Solar PV PanelsSolar Photovoltaics100 homes0.2 MW2022-113.7 yrs

Plus 9 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Mary Avenue, Birtley - Battery Energy Storage71 MWrefused 2026could supply ≈249,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Mrs Sharon Hodgson said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)