CONSTITUENCY BRIEFING · ENERGYMAP.APP

Thurrock

MP: Jen Craft (Labour) England Data to July 2026

Thurrock has 18 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 6,500 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 45,057 homes.

Ranks 206 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Aveley Landfill, Sandy Lane - PV Solar Array & BatteInfinis Energy Services Limited Solar 5,800 homes
16 MW
Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company
Ocado Operating Limited, New Purfleet Road - Solar Saber Renewable Energy Limited Solar 1,000 homes
2.8 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Intu Lakeside, West Thurrock Way - Solar PanelsGlobal Mutual Solar 500 homes
1.3 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.