No.192 of 650 · approved, not built MP: Gideon Amos (Liberal Democrat) England

Taunton and Wellington

Taunton and Wellington has 22 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 7,900 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.4m across the constituency's 47,337 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
22 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 7,900 homes. Approved at least two years ago; waiting on the grid, not on planning. That is 0.7× the renewable capacity actually running here.
9 projects · planning database (REPD), July 2026 · how we worked this out
£4.4m
is what the grid gap costs this constituency's 47,337 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 9 waiting projects · years since approval
Hollywood Bowl - Solar Voltaic Equipment 0.2 MW
4.5 YRS
Crown Industrial Estate, Venture Way - Solar Panels 0.7 MW
3.6 YRS
St Margarets Hospice, Heron Drive - Solar Panels 0.1 MW
3.6 YRS
Growth Technology Limited, Norton Fitzwarren - Solar Panels 0.2 MW
3.4 YRS
Wellington Sports Centre, Corams Lane - Solar Panels 0.2 MW
2.9 YRS
Foundation House, Culmhead - Solar Panels 0.3 MW
2.7 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Ham Farm, Creech St Michael - Solar ArraySolar Photovoltaics7,300 homes20.0 MW2024-062.1 yrs
Crown Industrial Estate, Venture Way - Solar PanelsSolar Photovoltaics300 homes0.7 MW2023-013.6 yrs
Foundation House, Culmhead - Solar PanelsSolar Photovoltaics100 homes0.3 MW2023-112.7 yrs
Growth Technology Limited, Norton Fitzwarren - Solar PanelsSolar Photovoltaics100 homes0.2 MW2023-033.4 yrs
Hollywood Bowl - Solar Voltaic EquipmentSolar Photovoltaics100 homes0.2 MW2022-014.5 yrs
Wellington Sports Centre, Corams Lane - Solar PanelsSolar Photovoltaics100 homes0.2 MW2023-092.9 yrs
St Margarets Hospice, Heron Drive - Solar PanelsSolar Photovoltaics100 homes0.1 MW2023-013.6 yrs
Rivergate House - Solar PanelsSolar Photovoltaics100 homes0.1 MW2023-112.7 yrs
Culmhead Business Park - Ground Mounted Photovoltaic Solar ArraySolar Photovoltaics— MW2024-012.6 yrs

Plus 1 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Fideoak Mills30 MWoperating 2018could supply ≈105,000 homes
Hele Manor Farm, Bradford On Tone - Battery Storage System20 MWapproved, not built 2023could supply ≈70,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →