CONSTITUENCY BRIEFING · ENERGYMAP.APP

Stretford and Urmston

MP: Andrew Western (Labour) England Data to July 2026

Stretford and Urmston has 1.8 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 700 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 41,881 homes.

Ranks 356 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Carrington Power Station, Manchester Road - Battery Statera Energy Battery
680 MW
Under constructionWho can move it: the developer
Daines Battery Energy Storage SystemSSE Daines BESS Limited Battery
600 MW
Cannot connect to the grid until 2028, 3 years after it was approvedWho can move it: the grid operator (NESO) and National Grid
Manchester Road - Green Hydrogen Production FacilityTrafford Green Hydrogen Limited Hydrogen
200 MW
Waiting 5.0 years for a planning decisionWho can move it: Trafford Council

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.