Stirling and Strathallan
Stirling and Strathallan has 52 MW of clean power (almost all onshore wind) approved and still not built: enough to supply a year's electricity to 42,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,517 homes. There is also 187 MW of wind running here on the local network. If that gets switched off, no national record shows it.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Shelloch Wind Farm | Wind Onshore | 21,000 homes | 24.0 MW | 2022-02 | 4.5 yrs |
| Strathallan Wind Farm | Wind Onshore | 18,000 homes | 20.7 MW | 2019-01 | 7.5 yrs |
| Rowan Gate - Solar Farm | Solar Photovoltaics | 2,500 homes | 7.0 MW | 2022-07 | 4.1 yrs |
| Airthrey Road - PV Solar Panels | Solar Photovoltaics | — | — MW | 2022-02 | 4.5 yrs |
Plus 6 more approved within the last two years.
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| Glenside Farm - Battery Storage | 400 MW | approved, not built 2025 | could supply ≈1,402,000 homes |
| Shindour, Feddal Hill Wood - Battery Energy Storage Facility | 50 MW | approved, not built 2024 | could supply ≈175,000 homes |
| Shindour - Energy Storage Facility | 50 MW | approved, not built 2021 | could supply ≈175,000 homes |
| Killin Switching Station, Boreland - Boreland Energy Storage Park | 43 MW | approved, not built 2025 | could supply ≈151,000 homes |
| Earlsburn Avenue - Earlsburn Wind Farm Extension | 18 MW | approved, not built 2025 | could supply ≈63,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →