CONSTITUENCY BRIEFING · ENERGYMAP.APP

Spelthorne

MP: Lincoln Jopp (Conservative) England Data to July 2026

Spelthorne has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,805 homes.

Ranks 569 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Sunbury Battery Energy Storage System - Battery EnerEcoDev Group Limited Battery
200 MW
Cannot connect to the grid until 2031, 5 years after it was approvedWho can move it: the grid operator (NESO) and National Grid
Long Lane, Stanwell - Battery Energy StorageHarwood Project One Limited Battery
50 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Charlton Lane Eco Park (ACT)SITA UK Advanced Conversion Technologies
3.6 MW
Under constructionWho can move it: the developer

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.