South Ribble has 4.4 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,600 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.7m across the constituency's 40,379 homes.

Ranks 271 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Penwortham - Battery storageShaw-Energi Limited Battery
57 MW
Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO)
Howick Hall Farm - Battery Storage FacilityPenwortham Storage Limited Battery
50 MW
Waiting 5.5 years for a planning decisionWho can move it: South Ribble Council
Vause Farm - Battery StorageSirius Renewable Energy Limited Battery
20 MW
Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company