Rossendale and Darwen
Rossendale and Darwen has 75 MW of renewables running, enough for 66,000 homes over a year, and nothing large waiting in the planning queue. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,080 homes. There is also 75 MW of wind running here on the local network. If that gets switched off, no national record shows it. A 85 MW battery was refused planning here in 2025; while discharging it could have supplied about 298,000 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Crown Paints, Hollins Road - Solar PV Panels | Solar Photovoltaics | 100 homes | 0.3 MW | 2023-04 | 3.3 yrs |
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| Rochdale Road, Edenfield - Battery Storage | 85 MW | refused 2025 | could supply ≈298,000 homes |
| Park Road Battery Storage | 10 MW | approved, not built 2021 | could supply ≈35,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →
What has Andy MacNae said about the grid in Parliament? Search Hansard →