Reading West and Mid Berkshire
Reading West and Mid Berkshire has 32 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 11,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.5m across the constituency's 37,931 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Bloomfield Hatch Farm - Solar Farm & Battery | Solar Photovoltaics | 9,400 homes | 25.8 MW | 2022-09 | 3.9 yrs |
| Sulhamstead Solar Field - Stud Farm | Solar Photovoltaics | 1,800 homes | 5.0 MW | 2017-04 | 9.3 yrs |
| Renegade Brewery, Frilsham - Solar Panels | Solar Photovoltaics | 200 homes | 0.5 MW | 2023-07 | 3.1 yrs |
| Hillfields, Burghfield Common - Solar Array | Solar Photovoltaics | 200 homes | 0.4 MW | 2023-11 | 2.7 yrs |
Plus 6 more approved within the last two years.
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →