Oldham West, Chadderton and Royton

MP: Jim McMahon (Labour (Co-op)) England Data to July 2026

Oldham West, Chadderton and Royton has 2.8 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 41,416 homes.

Ranks 306 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Whitegate Battery StoragePelagic Energy (Constantine Energy) Battery
57 MW
Under constructionWho can move it: the developer
Chadderton - Battery energy storage facilityField Battery
20 MW
Under constructionWho can move it: the developer
IGC, Lydia Becker Way - Solar PanelsAshcroft Electrical Services Limited Solar 1,100 homes
3.1 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company