CONSTITUENCY BRIEFING · ENERGYMAP.APP

North Warwickshire and Bedworth

MP: Rachel Taylor (Labour) England Data to July 2026

North Warwickshire and Bedworth has 80 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 29,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.6m across the constituency's 39,472 homes.

Ranks 81 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Hams Hall - Battery Energy Storage SystemWelbar Energy Storage Limited / Penso Power (B Battery
400 MW
Under constructionWho can move it: the developer
Hams Hall, Hams Lane - Battery Energy Storage SystemEon UK Plc Battery
98 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Marston Sewerage Pumping Station, Bodymoor Heath LanAnesco Limited Battery
50 MW
Waiting 1.2 years for a planning decisionWho can move it: North Warwickshire Council

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.