No.211 of 650 · approved, not built MP: Sadik Al-Hassan (Labour) England

North Somerset

North Somerset has 16 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 5,800 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 40,791 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
16 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 5,800 homes. Approved at least two years ago; waiting on the grid, not on planning.
5 projects · planning database (REPD), July 2026 · how we worked this out
£3.8m
is what the grid gap costs this constituency's 40,791 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

5 of 5 waiting projects · years since approval
Roper Rhodes Limited - Roof Solar PV 0.8 MW
4.8 YRS
Lower Strode Road - Solar Photovoltaic Panels 0.3 MW
3.9 YRS
Green Lane, Nempnett Thrubwell - Solar Farm 9.1 MW
3.8 YRS
David Lloyd Leisure Plc, Ashton Road - Solar PV panels 0.7 MW
2.9 YRS
Haberfield Park Farm - Solar Farm 5 MW
2.7 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Green Lane, Nempnett Thrubwell - Solar FarmSolar Photovoltaics3,300 homes9.1 MW2022-103.8 yrs
Haberfield Park Farm - Solar FarmSolar Photovoltaics1,800 homes5.0 MW2023-112.7 yrs
Roper Rhodes Limited - Roof Solar PVSolar Photovoltaics300 homes0.8 MW2021-104.8 yrs
David Lloyd Leisure Plc, Ashton Road - Solar PV panelsSolar Photovoltaics300 homes0.7 MW2023-092.9 yrs
Lower Strode Road - Solar Photovoltaic PanelsSolar Photovoltaics100 homes0.3 MW2022-083.9 yrs

Plus 7 more approved within the last two years.

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Sadik Al-Hassan said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)