North Herefordshire
North Herefordshire has 2.3 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 800 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 39,991 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Brierley Court Hop Farm, Brierley Lane - Solar Panels | Solar Photovoltaics | 200 homes | 0.6 MW | 2022-11 | 3.7 yrs |
| Woofferton Transmitting Station - Solar Panel Arrays | Solar Photovoltaics | 200 homes | 0.5 MW | 2024-03 | 2.4 yrs |
| Oakchurch Farm Shop, Staunton On Wye - Solar Array | Solar Photovoltaics | 100 homes | 0.3 MW | 2024-05 | 2.2 yrs |
| Manor Farm Solar Panels | Solar Photovoltaics | 100 homes | 0.3 MW | 2021-02 | 5.5 yrs |
| Shobdon Poultry Farm, Shobdon - Solar PV Array | Solar Photovoltaics | 100 homes | 0.3 MW | 2024-05 | 2.2 yrs |
| Morrisons Supermarket - Photovoltaic Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2022-11 | 3.7 yrs |
| The Hop Pocket - Solar Panels | Solar Photovoltaics | — | — MW | 2023-12 | 2.7 yrs |
Plus 3 more approved within the last two years.
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| Land to the west of Clay Hill Pit / Larport Farm | 20 MW | could supply ≈70,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →
What has Dr Ellie Chowns said about the grid in Parliament? Search Hansard →