No.26 of 650 · approved, not built MP: Alex Brewer (Liberal Democrat) England

North East Hampshire

North East Hampshire has 168 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 61,000 homes. No wind farm here is paid to switch off. Almost every pound of that money goes to wind farms in Scotland, held back by the crowded wires at the border. The cost is shared across every bill in Britain, so households here pay too: about £92 a year per household, £3.8m across the constituency's 41,059 homes. A 115 MW battery was refused planning here in 2026; while discharging it could have supplied about 403,000 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
168 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 61,000 homes — about as many homes as this constituency has. Approved at least two years ago; waiting on the grid, not on planning. That is 15.4× the renewable capacity actually running here.
5 projects · planning database (REPD), July 2026 · how we worked this out
£3.8m
is what the grid gap costs this constituency's 41,059 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

4 of 5 waiting projects · years since approval
Chosley Farm, North Warnborough Solar Farm a 50 MW
4.7 YRS
Bunkers Hill Farm - Solar farm & Battery sta 50 MW
4.7 YRS
Kiln Fields Solar Farm 18 MW
4.6 YRS
Bramley Frith Solar Farm 50 MW
3.5 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Chosley Farm, North Warnborough Solar Farm and Battery storageSolar Photovoltaics18,000 homes49.9 MW2021-114.7 yrs
Bramley Frith Solar FarmSolar Photovoltaics18,000 homes49.9 MW2023-023.5 yrs
Bunkers Hill Farm - Solar farm & Battery stationsSolar Photovoltaics18,000 homes49.9 MW2021-114.7 yrs
Kiln Fields Solar FarmSolar Photovoltaics6,500 homes17.9 MW2021-124.6 yrs
Bartley Wood Business Park - Solar panelsSolar Photovoltaics100 homes0.1 MW2023-073.0 yrs

Plus 1 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Frog Lane, Little London - Battery Energy Storage115 MWrefused 2026could supply ≈403,000 homes
Minchens Lane Battery Storage Facility100 MWoperating 2023could supply ≈350,000 homes
Penn Croft Farm, Crondall - Battery Energy Storage Facility100 MWapproved, not built 2023could supply ≈350,000 homes
Bowenhurst Farm, Mill Lane - Battery Energy Storage100 MWrefused 2026could supply ≈350,000 homes
Crondall Road, Crondall - Fleet Bramley Battery Energy Storage100 MWapproved, not built 2025could supply ≈350,000 homes
Ash Lane, Little London - Battery Storage57 MWapproved, not built 2023could supply ≈200,000 homes
Coxmoor Wood, Crondall Road - Battery Storage57 MWapproved, not built 2024could supply ≈200,000 homes
Withy Place, Bramley Road - Battery Energy Storage50 MWapproved, not built 2025could supply ≈175,000 homes
Rye Common50 MWapproved, not built 2021could supply ≈173,000 homes
Blue Bell Lodge, Rye Common Lane - Battery Storage50 MWapproved, not built 2023could supply ≈173,000 homes
Basing Road20 MWcould supply ≈70,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Read the full method, including everything we cannot see →

What has Alex Brewer said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)