No.274 of 650 · approved, not built MP: Jessica Morden (Labour) Wales

Newport East

Newport East has 4.2 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,500 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 45,644 homes.

Not visible
here
13 MW of wind is running in this constituency, but it sits on the local network rather than the national grid — so if it is paid to switch off, no national record shows it. That is why this seat has no figure here: not because nothing happens, but because nobody publishes it. The £ figure for this seat is a floor, not a zero.
4.2 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 1,500 homes. Approved at least two years ago; waiting on the grid, not on planning.
2 projects · planning database (REPD), July 2026 · how we worked this out
£4.2m
is what the grid gap costs this constituency's 45,644 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

2 of 2 waiting projects · years since approval
Docks Way Solar Farm 2.4 MW
4.7 YRS
New Venture Buildings, Caswell Way - Solar Array 1.8 MW
3.4 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Docks Way Solar FarmSolar Photovoltaics900 homes2.4 MW2021-124.7 yrs
New Venture Buildings, Caswell Way - Solar ArraySolar Photovoltaics700 homes1.8 MW2023-033.4 yrs

Plus 2 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Uskmouth Power Station - Battery Storage230 MWbeing built 2022could supply ≈806,000 homes
Uskmouth Power Station, West Nash Road - Battery Storage Facility120 MWbeing built 2024could supply ≈420,000 homes
Leeway House, Leeway Industrial Estate - Battery Energy Storage System21 MWapproved, not built 2025could supply ≈72,000 homes
Traston Road20 MWoperating 2016could supply ≈70,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →