Milton Keynes Central
Milton Keynes Central has 7.3 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 2,600 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.5m across the constituency's 48,798 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Chippenham Drive, Kingston - Solar Panels | Solar Photovoltaics | 600 homes | 1.8 MW | 2024-07 | 2.1 yrs |
| A G Barr Plc, Crossley Drive - Solar Panels | Solar Photovoltaics | 300 homes | 0.9 MW | 2023-12 | 2.6 yrs |
| Thornbury, West Ashland - Solar Photovoltaic System | Solar Photovoltaics | 300 homes | 0.9 MW | 2023-03 | 3.4 yrs |
| Northfield Drive, Northfield - Solar Panles | Solar Photovoltaics | 300 homes | 0.8 MW | 2022-03 | 4.3 yrs |
| David Lloyd, Livingstone Drive - Solar Panels | Solar Photovoltaics | 200 homes | 0.6 MW | 2023-11 | 2.7 yrs |
| Midway Centre, Harding Road - Solar Panels | Solar Photovoltaics | 200 homes | 0.5 MW | 2023-07 | 3.0 yrs |
| Bradwell Road, Loughton Lodge - Solar Panels | Solar Photovoltaics | 200 homes | 0.5 MW | 2022-06 | 4.1 yrs |
| Gosh Foods, Maidstone Road - Solar Panels | Solar Photovoltaics | 200 homes | 0.5 MW | 2023-02 | 3.5 yrs |
| Northfield Drive, Northfield Drive - Solar Panels | Solar Photovoltaics | 100 homes | 0.3 MW | 2024-03 | 2.4 yrs |
| Deltic Avenue, Rooksley - Solar Panels | Solar Photovoltaics | 100 homes | 0.3 MW | 2024-05 | 2.2 yrs |
| Fen Street- Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2022-05 | 4.2 yrs |
| Winterhill House - Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2021-11 | 4.7 yrs |
Plus 3 more approved within the last two years.
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →