No.44 of 650 · approved, not built MP: George Freeman (Conservative) England

Mid Norfolk

Mid Norfolk has 129 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 47,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 40,731 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
129 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 47,000 homes — about as many homes as this constituency has. Approved at least two years ago; waiting on the grid, not on planning. That is 3.4× the renewable capacity actually running here.
11 projects · planning database (REPD), July 2026 · how we worked this out
£3.7m
is what the grid gap costs this constituency's 40,731 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

4 of 11 waiting projects · years since approval
Three Bridges Solar Farm 15 MW
5.4 YRS
Attleborough Road Solar Farm 30 MW
4.8 YRS
Colton - Solar photovoltaic farm, Battery storage 30 MW
4.1 YRS
Jafa, Great Dunham - Solar Photovoltaic Farm & Battery Storage 50 MW
3.3 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Jafa, Great Dunham - Solar Photovoltaic Farm & Battery StorageSolar Photovoltaics18,000 homes49.9 MW2023-033.3 yrs
Attleborough Road Solar FarmSolar Photovoltaics11,000 homes30.0 MW2021-104.8 yrs
Colton - Solar photovoltaic farm, Battery storageSolar Photovoltaics11,000 homes30.0 MW2022-064.1 yrs
Three Bridges Solar FarmSolar Photovoltaics5,400 homes15.0 MW2021-035.4 yrs
Little Cressingham, Cranswick Country Foods - Solar ArraySolar Photovoltaics700 homes1.8 MW2023-033.4 yrs
Land North of the A11 - Solar ParkSolar Photovoltaics400 homes1.0 MW2022-103.8 yrs
Cranswick Country Foods, Brandon Road - Solar PanelsSolar Photovoltaics200 homes0.7 MW2022-123.6 yrs
Station Road - Solar PanelsSolar Photovoltaics100 homes0.3 MW2022-044.3 yrs
IFD Group, Harling Road - Solar PanelsSolar Photovoltaics100 homes0.2 MW2023-023.4 yrs
Lays Farm, Wood Lane - Solar PanelsSolar Photovoltaics100 homes0.2 MW2022-103.8 yrs
Dereham Leisure Centre, Station Road - Solar PanelsSolar Photovoltaics100 homes0.2 MW2024-012.6 yrs

Plus 2 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
The Park Farm, Birds Corner - Battery Energy Storage800 MWcould supply ≈2,803,000 homes
Colton - Solar photovoltaic farm, Battery storage30 MWbeing built 2022could supply ≈105,000 homes
Three Bridges Solar Farm15 MWapproved, not built 2021could supply ≈53,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →