No.309 of 650 · approved, not built MP: Mr Peter Bedford (Conservative) England

Mid Leicestershire

Mid Leicestershire has 2.8 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.8m across the constituency's 41,841 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
2.8 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 1,000 homes. Approved at least two years ago; waiting on the grid, not on planning. That is 0.1× the renewable capacity actually running here.
6 projects · planning database (REPD), July 2026 · how we worked this out
£3.8m
is what the grid gap costs this constituency's 41,841 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 6 waiting projects · years since approval
Laura Ashley, Stanton Under Bardon - Solar panels 0.5 MW
5.6 YRS
Kirby Road Solar Panels 0.5 MW
5.5 YRS
West Beacon Solar Park 0.8 MW
5.3 YRS
Centurion Way, Braunstone Town - Solar Panels 0.2 MW
4.8 YRS
Unit F, Meridian Leisure Park, Braunstone Town - Solar Array
3.1 YRS
Roman Avenue, Unit A - Solar PV System 0.8 MW
2.4 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Roman Avenue, Unit A - Solar PV SystemSolar Photovoltaics300 homes0.8 MW2024-032.4 yrs
West Beacon Solar ParkSolar Photovoltaics300 homes0.8 MW2021-045.3 yrs
Kirby Road Solar PanelsSolar Photovoltaics200 homes0.5 MW2021-025.5 yrs
Laura Ashley, Stanton Under Bardon - Solar panelsSolar Photovoltaics200 homes0.5 MW2020-125.6 yrs
Centurion Way, Braunstone Town - Solar PanelsSolar Photovoltaics100 homes0.2 MW2021-104.8 yrs
Unit F, Meridian Leisure Park, Braunstone Town - Solar ArraySolar Photovoltaics— MW2023-063.1 yrs

Plus 4 more approved within the last two years.

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →