CONSTITUENCY BRIEFING · ENERGYMAP.APP

Mid Cheshire

MP: Andrew Cooper (Labour) England Data to July 2026

Mid Cheshire has 23 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 8,200 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 40,547 homes.

Ranks 190 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
LostockTata Chemicals Europe (formerly Brunner Mond & EfW Incineration
60 MW
Under constructionWho can move it: the developer
Wallerscote Limebeds - Battery Energy StorageInfinis Solar Developments Limited / Green Ear Battery
30 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company
Wallerscote Limebeds - Solar Pv ParkInfinis Solar Developments Limited / Green Ear Solar 8,000 homes
22 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing