CONSTITUENCY BRIEFING · ENERGYMAP.APP

Luton South and South Bedfordshire

MP: Rachel Hopkins (Labour) England Data to July 2026

Luton South and South Bedfordshire has 4.5 MW of clean power (mostly solar) approved and still not built: enough to supply a year's electricity to 2,400 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.1m across the constituency's 44,991 homes.

Ranks 270 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Watling Street, Caddington - Solar FarmChiltern Renewables Hockliffe Limited Solar 7,100 homes
20 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Astral Green - Wind Turbine, Solar Array & Battery EArnold White Estates Limited Solar 800 homes
2.1 MW
Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company
Astral Green - Wind Turbine, Solar Array & Battery EArnold White Estates Limited Onshore wind 1,300 homes
1.5 MW
Approved 2 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.