No.412 of 650 · approved, not built MP: Maria Eagle (Labour) England

Liverpool Garston

Liverpool Garston has 1.1 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 400 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.8m across the constituency's 40,890 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
1.1 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 400 homes. Approved at least two years ago; waiting on the grid, not on planning.
3 projects · planning database (REPD), July 2026 · how we worked this out
£3.8m
is what the grid gap costs this constituency's 40,890 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

3 of 3 waiting projects · years since approval
Garston Shore Road - Solar Panels 0.5 MW
3.8 YRS
Renaissance Way - Plot 7 Solar PV Array
2.6 YRS
Estuary Boulevard - Solar Panels 0.6 MW
2.4 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Estuary Boulevard - Solar PanelsSolar Photovoltaics200 homes0.6 MW2024-032.4 yrs
Garston Shore Road - Solar PanelsSolar Photovoltaics200 homes0.5 MW2022-093.8 yrs
Renaissance Way - Plot 7 Solar PV ArraySolar Photovoltaics— MW2023-122.6 yrs

Plus 1 more approved within the last two years.

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →