No.292 of 650 · approved, not built MP: Liz Kendall (Labour) England

Leicester West

Leicester West has 3.8 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 1,400 homes. Britain's grid bottlenecks still add to bills here: about £116 a year per household, £5.5m across the constituency's 47,499 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
3.8 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 1,400 homes. Approved at least two years ago; waiting on the grid, not on planning.
4 projects · planning database (REPD), July 2026 · how we worked this out
£5.5m
is what the grid gap costs this constituency's 47,499 households in a year between them — £116 each, about 65 days of one home's electricity.
The £116 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

4 of 4 waiting projects · years since approval
Granby Road - Solar PV Panels & Air Source Heat Pumps
4.7 YRS
Bingo Club, Beaumont Way - Solar Panels 0.4 MW
3.1 YRS
Pepsico International Limited, Leycroft Road - Solar Panels 3.2 MW
2.7 YRS
Ashton Business Park, Ashton Close - Solar Array 0.2 MW
2.2 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Pepsico International Limited, Leycroft Road - Solar PanelsPepsico International Limited, Leycroft RoadSolar Photovoltaics1,200 homes3.2 MW2024-032.7 yrs
Bingo Club, Beaumont Way - Solar PanelsBingo Club, 100 Beaumont Way, LeicesterSolar Photovoltaics100 homes0.4 MW2023-093.1 yrs
Ashton Business Park, Ashton Close - Solar Array10 Ashton Business ParkSolar Photovoltaics100 homes0.2 MW2024-082.2 yrs
Granby Road - Solar PV Panels & Air Source Heat PumpsGranby Primary School, Granby Road, LeicesterSolar Photovoltaics—— MW2022-034.7 yrs

Plus 2 more approved within the last two years.

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Liz Kendall said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)