No.377 of 650 · approved, not built MP: Anneliese Midgley (Labour) England

Knowsley

Knowsley has 1.5 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 500 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 40,161 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
1.5 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 500 homes. Approved at least two years ago; waiting on the grid, not on planning.
4 projects · planning database (REPD), July 2026 · how we worked this out
£3.7m
is what the grid gap costs this constituency's 40,161 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

4 of 4 waiting projects · years since approval
Knowsley Industrial Park 0.3 MW
5.6 YRS
David Lloyd Leisure, Arbour Lane - Solar Panels
3.0 YRS
Adlib House, Kitling Road - Solar Panels 0.2 MW
2.9 YRS
Charley Wood Road, Knowsley Industrial Park - Solar Photovoltaics 0.9 MW
2.8 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Charley Wood Road, Knowsley Industrial Park - Solar PhotovoltaicsSolar Photovoltaics300 homes0.9 MW2023-102.8 yrs
Knowsley Industrial ParkSolar Photovoltaics100 homes0.3 MW2021-015.6 yrs
Adlib House, Kitling Road - Solar PanelsSolar Photovoltaics100 homes0.2 MW2023-092.9 yrs
David Lloyd Leisure, Arbour Lane - Solar PanelsSolar Photovoltaics— MW2023-083.0 yrs

Plus 3 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Perimeter Road, Kirkby - Battery Energy Storage165 MWcould supply ≈578,000 homes
Cut Lane - Battery Energy Storage System57 MWcould supply ≈200,000 homes
Coopers Lane, Kirkby - Battery Storage Facility50 MWapproved, not built 2024could supply ≈173,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Anneliese Midgley said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)