No.79 of 650 · approved, not built MP: Lillian Jones (Labour) Scotland

Kilmarnock and Loudoun

Kilmarnock and Loudoun was paid £900k last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 11 days. A further 82 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 71,000 homes. A 500 MW battery approved at Kilmarnock Battery Energy Storage System in 2025 would store power that is currently wasted; it has not been built.

£900k
paid to wind farms here not to generate in the last year — enough to pay for every household here's electricity for 11 days.
Elexon balancing data, 12 months to 31 Jul 2026 · No.16 of 19 seats with visible switch-offs · how we worked this out
82 MW
of clean power — almost all onshore wind — approved and still not built, enough to supply a year's electricity to 71,000 homes — about as many homes as this constituency has. Approved at least two years ago; waiting on the grid, not on planning. That is 0.3× the renewable capacity actually running here.
6 projects · 81 MW onshore wind, 0.8 MW solar · planning database (REPD), July 2026 · how we worked this out
£4.1m
is what the grid gap costs this constituency's 44,098 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 6 waiting projects · years since approval
Sneddon Law Community Wind Farm 45 MW
13.4 YRS
Moorfield North Industrial Park, Moorfield
5.4 YRS
Hare Craig Windfarm 36 MW
4.1 YRS
Auldhouseburn Farm, Muirkirk - Solar Panels 0.2 MW
3.2 YRS
Cummnock Waste Water Treatment Works - Solar Panels 0.5 MW
3.1 YRS
Kilmarnock Academy, Elmbank Drive - Solar PV System 0.2 MW
2.7 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Sneddon Law Community Wind FarmWind Onshore39,000 homes45.0 MW2013-0213.4 yrs
Hare Craig WindfarmWind Onshore31,000 homes36.0 MW2022-074.1 yrs
Cummnock Waste Water Treatment Works - Solar PanelsSolar Photovoltaics200 homes0.5 MW2023-063.1 yrs
Auldhouseburn Farm, Muirkirk - Solar PanelsSolar Photovoltaics100 homes0.2 MW2023-053.2 yrs
Kilmarnock Academy, Elmbank Drive - Solar PV SystemSolar Photovoltaics100 homes0.2 MW2023-112.7 yrs
Moorfield North Industrial Park, MoorfieldSolar Photovoltaics— MW2021-035.4 yrs

Plus 2 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Kilmarnock Battery Energy Storage System500 MWapproved, not built 2025could supply ≈1,752,000 homes
Kilmarnock South Substation - Battery storage300 MWoperatingcould supply ≈1,051,000 homes
Holmquarry Road - Battery Storage60 MWapproved, not built 2025could supply ≈212,000 homes
Inchbean Farm, Treeswoodhead Road - Battery Energy Storage System60 MWapproved, not built 2025could supply ≈210,000 homes
Hare Craig Windfarm14 MWapproved, not built 2022could supply ≈49,000 homes

Wind farms paid to switch off

12 months to 31 Jul 2026 · mapping confidence shown · mapping file
SitePaid, 12 monthsEnergy lostConfidence
Whitelee Windfarm Extension phase 2£450ka year of 2,100 homes' electricityhigh
Whitelee Windfarm Extension Phase 1£450ka year of 2,100 homes' electricityhigh

What this page does not show

The switch-off figure covers the big wind farms on the national grid only; smaller farms on the local grid are switched off invisibly, so it is a floor. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Lillian Jones said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)