No.82 of 650 · approved, not built MP: Lillian Jones (Labour) Scotland

Kilmarnock and Loudoun

Kilmarnock and Loudoun was paid £1.4m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 17 days. A further 82 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 71,000 homes. A 500 MW battery approved at Kilmarnock Battery Energy Storage System in 2025 would store power that is currently wasted; it has not been built.

£1.4m
paid to wind farms here not to generate in the last year — enough to pay for every household here's electricity for 17 days.
Elexon balancing data, 2025-11-01 to 2026-10-31 · No.16 of 19 seats with visible switch-offs · how we worked this out
82 MW
of clean power — almost all onshore wind — approved and still not built, enough to supply a year's electricity to 71,000 homes — about as many homes as this constituency has. Approved at least two years ago; waiting on the grid, not on planning. That is 0.3× the renewable capacity actually running here.
6 projects · 81 MW onshore wind, 0.8 MW solar · planning database (REPD), July 2026 · how we worked this out
£5.1m
is what the grid gap costs this constituency's 44,098 households in a year between them — £116 each, about 65 days of one home's electricity.
The £116 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 6 waiting projects · years since approval
Sneddon Law Community Wind Farm 45 MW
13.7 YRS
Moorfield North Industrial Park, Moorfield
5.7 YRS
Hare Craig Windfarm 36 MW
4.3 YRS
Auldhouseburn Farm, Muirkirk - Solar Panels 0.2 MW
3.5 YRS
Cummnock Waste Water Treatment Works - Solar Panels 0.5 MW
3.4 YRS
Kilmarnock Academy, Elmbank Drive - Solar PV System 0.2 MW
3.0 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Sneddon Law Community Wind FarmSneddon Law Off Hemphill Road MoscowWind Onshore39,000 homes45.0 MW2013-0213.7 yrs
Hare Craig WindfarmLand At Hare Craig, Muirkirk, Cumnock, StrathclydeWind Onshore31,000 homes36.0 MW2022-074.3 yrs
Cummnock Waste Water Treatment Works - Solar PanelsUnderwood Private Depot Off Auchinleck Road CumnockSolar Photovoltaics200 homes0.5 MW2023-063.4 yrs
Auldhouseburn Farm, Muirkirk - Solar PanelsAuldhouseburn Farm, Muirkirk, CumnockSolar Photovoltaics100 homes0.2 MW2023-053.5 yrs
Kilmarnock Academy, Elmbank Drive - Solar PV SystemKilmarnock Academy, 15 Elmbank Drive, KilmarnockSolar Photovoltaics100 homes0.2 MW2023-113.0 yrs
Moorfield North Industrial Park, MoorfieldUnit 7 Moorfield North Industrial Park, Neephill View, MoorfieldSolar Photovoltaics—— MW2021-035.7 yrs

Plus 2 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Kilmarnock Battery Energy Storage System500 MWapproved, not built 2025could supply ≈1,752,000 homes
Kilmarnock South Substation - Battery storage300 MWoperatingcould supply ≈1,051,000 homes
Holmquarry Road - Battery Storage60 MWapproved, not built 2025could supply ≈212,000 homes
Inchbean Farm, Treeswoodhead Road - Battery Energy Storage System60 MWapproved, not built 2025could supply ≈210,000 homes
Hare Craig Windfarm14 MWapproved, not built 2022could supply ≈49,000 homes

Wind farms paid to switch off

2025-11-01 to 2026-10-31 · mapping confidence shown · mapping file
SitePaid, 12 monthsEnergy lostConfidence
Whitelee Windfarm Extension phase 2£690ka year of 3,100 homes' electricityhigh
Whitelee Windfarm Extension Phase 1£690ka year of 3,100 homes' electricityhigh

What this page does not show

The switch-off figure covers the big wind farms on the national grid only; smaller farms on the local grid are switched off invisibly, so it is a floor. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Lillian Jones said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)