CONSTITUENCY BRIEFING · ENERGYMAP.APP

Kettering

MP: Rosie Wrighting (Labour) England Data to July 2026

Kettering has 49 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 18,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.2m across the constituency's 46,190 homes. There is also 56 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 142 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Eckland Lodge Farm, Braybrooke - Battery Energy StorRegener8 Power Limited Battery
500 MW
Waiting 1.0 years for a planning decisionWho can move it: North Northamptonshire Council
Braybrooke Battery Energy Storage SystemAura Power Developments Limited Battery
500 MW
Waiting 1.0 years for a planning decisionWho can move it: North Northamptonshire Council
Braybrooke Village North, Harborough Road - Battery Elmya Energy Limited Battery
252 MW
Waiting 1.0 years for a planning decisionWho can move it: North Northamptonshire Council

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.